Subject: Civil Construction & Project Management
Level: Advanced Vocational Application
You are the site supervisor for a rural infrastructure project. You have been tasked with constructing a cylindrical concrete water tank. Your objective is to calculate the precise volume of wet concrete required, determine the dry volume of materials needed based on standard shrinkage factors, and generate a final Cost Estimate (Bill of Quantities) for the client.
| Parameter | Value |
|---|---|
| Inner Radius of Tank ($r$) | 2.0 meters |
| Inner Height of Tank ($h$) | 3.5 meters |
| Thickness of Walls ($t_w$) | 0.15 meters (15 cm) |
| Thickness of Base Slab ($t_b$) | 0.20 meters (20 cm) |
| Concrete Mix Ratio (Cement : Sand : Aggregate) | 1 : 1.5 : 3 (M20 Grade equivalent) |
| Dry Volume Coefficient | 1.54 (Standard safety factor for voids/shrinkage) |
We must calculate the volume of the base slab and the volume of the hollow cylindrical walls separately.
A. Base Slab Volume ($V_{base}$)
The base extends to the outer edge of the walls. Therefore, the Outer Radius ($R$) is the Inner Radius ($r$) + Wall Thickness ($t_w$).
B. Wall Volume ($V_{walls}$)
The walls are a hollow cylinder. We calculate the area of the ring annulus and multiply by height.
C. Total Wet Volume
$$V_{total} = 2.904 + 6.845 = \mathbf{9.749 \, m^3}$$Wet concrete shrinks when it dries. To find the quantity of raw materials to purchase, we multiply the wet volume by the Dry Volume Coefficient (1.54).
$$V_{dry} = 9.749 \times 1.54 = \mathbf{15.013 \, m^3}$$The mix ratio is 1 : 1.5 : 3. The sum of the ratio parts is:
$$Sum = 1 + 1.5 + 3 = 5.5$$A. Cement Quantity
$$Volume_{cement} = \frac{1}{5.5} \times 15.013 = 2.729 \, m^3$$To convert to bags (1 bag $\approx$ 0.0347 $m^3$):
$$Bags = \frac{2.729}{0.0347} \approx 78.6$$Note: Always round up for procurement. Total: 79 Bags.
B. Sand Quantity
$$Volume_{sand} = \frac{1.5}{5.5} \times 15.013 = 4.094 \, m^3$$C. Aggregate Quantity
$$Volume_{agg} = \frac{3}{5.5} \times 15.013 = 8.189 \, m^3$$| Item | Quantity | Rate | Total Cost ($) |
|---|---|---|---|
| Cement | 79 Bags | $8.00 / bag | $632.00 |
| Sand | 4.094 $m^3$ | $45.00 / $m^3$ | $184.23 |
| Aggregate | 8.189 $m^3$ | $40.00 / $m^3$ | $327.56 |
| Material Subtotal | $1,143.79 | ||
| Labor | 9.749 $m^3$ (wet) | $120.00 / $m^3$ | $1,169.88 |
| Gross Total | $2,313.67 |
Final Calculation with Contingency Tax (5%)
$$Final Cost = 2313.67 \times 1.05 = \mathbf{\$2,429.35}$$